CASE STUDY
Name of Project
BALLYROAN SEWAGE TREATMENT WORKS
Address: Ballyroan Co. Laois
Client: Laois County Council
Engineer/Client Contact Details: Neil Delaney, Nicholas O'Dwyer, Consulting Engineers, Carrick House, Dundrum Centre, Dub 14. Ph: 01 2984499
Completion Date: September 2003
Population Equivalent: 800 P.E.
Value: € 197,000 + Vat
BMS Design Details: BMS was responsible for all design, supply, pumping, 2 no. BMS BL 4000 Blivet Units, flow measurement, ferric dosing system, all ducting, pipework, m & e and civils within the curtilege of the treatment plant.
BMS Construction/Installation Details: BMS was responsible for the design of the civil works for the treatment plant, but excluding the execution.
BMS Operation/Maintenance Details: It is understood that the client is considering the awarding of an ongoing operating contract on completion of the final snag list.